A report of compliance must be obtained from the District before the municipal construction official can issue a Certificate of Occupancy. Inspection requests require 2 days notice.
Types of Compliance
Conditional: A conditional report is issued for the temporary stabilization of staggered occupancy projects or during the non-growing season. Compliance with all other requirements of the certified Soil Erosion and Sediment Control Plan is also required.
Complete: A final report is issued when permanent stabilization is established on the entire project. The projects is final graded, top-soiled, limed, fertilized, seeded, mulched and tacked and all permanent features of the erosion control plan have been installed.
Click here to dowload the Reports of Compliance form.